Acceptance testing and qualification: proving that it works

On this page
Test strategy, acceptance test book written with the business, representative test data, aptitude then regular service verification, quantified criteria.
Acceptance testing is not an end-of-project phase, it is a contract written at the start. It rests on three deliverables: a test strategy stating who tests what, an acceptance test book written with the business, and quantified acceptance criteria settled before the first line of code. It closes with two milestones, the aptitude verification and then the regular service verification, each recorded in a signed report.
It is the counterpart of data governance: there we proved the data was faithful, here we prove the function is compliant. In both cases the proof is prepared at the beginning, because at the end it is too late to invent the baseline you were going to compare against.
Why acceptance testing fails
Four causes, always the same, and none of them technical.
The test book is written by the supplier. That suits everyone, and it guarantees blind spots: the supplier tests what it understood, therefore what it built. The cases it misunderstood are not in the book.
The test data is invented. Mr John Test, 1 Main Street, orders a quantity of one. The system passes, and production hits a customer with two addresses, a foreign VAT number and an open credit note.
Acceptance criteria are not quantified. “The system must be fast” cannot be verified, therefore blocks nothing, therefore serves nothing. Without a threshold, every defect becomes a negotiation.
And the business discovers the application during acceptance. It then asks for changes that are legitimate but out of scope, and the project starts slipping at the precise moment it should be freezing.
The test strategy: who tests what
A test strategy fits on one page and answers a single question: at which level is each risk covered, and by whom. On a business application there are six useful levels.
- Unit tests. Owned by the development team, covering calculation rules and edge cases. Automated by construction, run on every change.
- Integration tests. They check that components talk to each other: database, external services, authentication, email delivery. This is where the most expensive production failures hide.
- End-to-end tests. They replay a full journey in a browser, on the three or four scenarios that keep the business running. Few and robust, rather than many and brittle.
- Business acceptance. Run by users against the test book. It is the only level that verifies functional correctness, the thing no automated test can judge.
- Performance tests. With realistic volumes and quantified thresholds, not on a dataset of ten records.
- Cross-cutting tests. Security, accessibility, browser compatibility. They follow existing standards and are planned like the rest.
The arbitration principle is simple: automate what is repetitive and objective, reserve humans for what requires judgement. Having a user review the same form fifty times is waste; asking them whether the generated document is the one they would send a client is irreplaceable.
The test book is written with the business
A useful test case contains five elements: the starting context, the data used, the steps, the expected result stated without ambiguity, and a criticality level. Without the expected result it is not a test, it is a guided tour.
The book must follow business processes, not screens. You do not test “the quote creation screen”, you test “produce a quote for an existing customer, get it approved, turn it into an order”. A screen-based split yields a book that passes in full while the process does not work.
Our workshop method comes down to three questions asked of users. What are the five business actions you perform most often? What are the three cases that caused you trouble this year? And what, if it stopped working, would prevent you from working tomorrow morning? The answers to the third question become the blocking cases, and they are almost never the ones anyone anticipated.
This work starts with the requirements document, which is in fact the right moment to write it, as we set out in our article on writing project specifications.
Test data: the most neglected item
A test is only worth its data. So you have to build a representative dataset, and that is work in itself, planned and assigned to someone.
Three ingredients. Nominal cases, representing the bulk of the volume. Edge cases, supplied by the business, meaning the odd records they know by heart and nobody else imagines. And realistic volumes for performance testing: measuring a response time on an empty database tells you nothing.
Beware the reflex of copying production into the test environment. With personal data that requires a legal basis and appropriate measures, and the minimisation principle applies to test environments too. The healthy approach is to anonymise or pseudonymise before copying, and to carry over only the fields the tests need. We detailed those requirements in our article on data governance and quality.
Aptitude verification, then regular service verification
For French public projects the vocabulary is set by the general administrative clauses for information and communication technology contracts, approved by the order of 30 March 2021. And it holds a surprise: the text does not say “verification of aptitude for proper functioning”, the acronym everyone uses, but simply “aptitude verification”. The acronym is a habit, not a reference.
Article 32 organises qualitative verification in two stages. The aptitude verification takes place after commissioning and establishes that the deliverables have the technical characteristics making them fit to perform their functions. If, and only if, the decision is positive, the regular service verification begins. Source: article 32.
That second stage observes the regularity of the service for thirty days from the positive aptitude decision. The service is deemed regular if cumulative unavailability attributable to each hardware element does not exceed 2% of actual usage time, counted from eight in the morning to six in the evening, Monday to Friday, public holidays excluded.
A practitioner’s note on that threshold: it is written for hardware. Transposed as is to business software, it leaves questions open, for instance whether general slowness counts as unavailability. That is the sort of point to settle in the contract’s specific clauses rather than discover during the observation period.
The deadlines, and the silence that means acceptance
Article 33 sets the decision deadlines, and both sides of the table should know them. Source: article 33.
For aptitude, the buyer has thirty days from the written notice in which the supplier states that the deliverables are ready for verification, or failing that from notification of the commissioning report.
For regular service, the deadline drops to a maximum of seven days, and silence means acceptance: absent notification within that period, the result is deemed positive and the deliverables are deemed accepted. For the buyer, that means a file left on a desk for a week counts as acceptance. For the supplier, it means the end of the observation period is a date to watch closely.
If the regular service result is negative, three decisions are possible: adjournment, with regularity verified over a further period of up to thirty days, acceptance with a price reduction proportionate to the imperfections, or rejection. Acceptance can also be limited to the elements whose regularity was verified, provided they remain usable under conditions the buyer finds acceptable.
Finally, article 34 states that an adjournment must be reasoned and invites the supplier to re-present the deliverables within fifteen days, and that the buyer’s silence beyond fifteen days after the supplier’s response counts as rejection. The clock runs both ways, which is what makes the framework balanced.
Acceptance criteria, in numbers
This is what turns acceptance into a decision rather than a negotiation. Four families of criteria are enough, provided they are all quantified and settled before you start.
Functional coverage: the share of test cases executed and passed, for instance one hundred percent of blocking cases and at least ninety-five percent overall. Residual defects: zero blocking defects, and an explicitly tolerated maximum number of major ones, with a dated commitment to fix.
Performance: a response time expressed as a percentile rather than an average, for instance ninety-five percent of pages served under one second at target volume. An average hides the spikes, and spikes are what users remember. For public pages, the Core Web Vitals thresholds provide a shared, measurable reference.
And cross-cutting criteria: an accessibility conformance level, which can be anchored to the official framework as we explained in our article on digital accessibility, plus the absence of known critical vulnerabilities at go-live.
One last point that prevents half the arguments: defect classification is defined in advance. Blocking means the business process is stopped with no workaround. Major means an acceptable workaround exists. Minor means it is annoying but does not affect the work. Without those written definitions, every defect is blocking to whoever reports it and minor to whoever has to fix it.
Automated regression testing, and what it costs
An automated test suite is not free: it is developed, it is maintained, and it breaks when the interface changes. The classic mistake is trying to automate everything, producing a slow, brittle suite the team ends up switching off.
The right priority order is economic. Automate first the journeys whose interruption costs money: ordering, payment, record creation, login. Then the calculation rules, which are easy to test without an interface and whose regressions are silent. Only then the rest, if time allows.
Two indicators are enough to steer this: the total runtime of the suite, which must stay compatible with running on every change, and the share of flaky tests, meaning those that fail for no reason. Beyond a few percent, the team stops believing the results, and a suite nobody believes protects nothing.
The signed reports, and what they trigger
Each milestone produces a document, and these are not bureaucracy: they start the clocks, trigger payments and open the warranty. The commissioning report, delivered by the supplier, opens the aptitude verification. The aptitude decision opens the regular service observation period. The acceptance decision takes effect on the date it is notified, or at the end of the seven-day period in the case of tacit acceptance.
A method note for private projects, where none of this is imposed: adopt the structure anyway. Two milestones, an observation period under real conditions, symmetrical decision deadlines and signed reports. It is not administrative formalism, it is what lets you say on a precise day that the project is delivered. Without it, a project is never finished, it just fades.
What we take away from it
Acceptance is won at the start. A one-page test strategy, a book written with the business and structured by process, a dataset built from the records that actually caused trouble, and quantified acceptance criteria with a defect classification defined before hostilities open.
The French public framework provides a structure worth adopting even outside public contracts: aptitude verification, then thirty days observing regular service, then a decision within a short window where silence means acceptance. And the text says “aptitude verification”, not the acronym everyone uses.
We build business applications with that discipline, because it is what makes a go-live uneventful. Our business application page sets out how we work, and if you are preparing acceptance on a live project, let’s talk.
FAQ
Frequently asked questions
What is an acceptance test plan, and who should write it?
It is the document that lists the test cases to run to validate an application. Each case includes a starting context, the data used, the steps, the expected result stated without ambiguity, and a criticality level. It must be written with the business users and structured by process rather than by screen, because a plan written by the vendor only tests what the vendor understood, and therefore what the vendor built.
What is the difference between the aptitude check and the regular service check?
The general administrative terms applicable to information technology contracts, approved by the order of March 30, 2021, organizes qualitative checks in two stages. The aptitude check establishes that the services have the technical characteristics that make them fit to perform their functions. If the decision is positive, the regular service check begins and observes operation for thirty days under real conditions. Note that the text says "aptitude check," not "check of fitness for proper operation."
How long does the regular service check last?
Thirty days from the positive aptitude check decision. The service is deemed regular if the total unavailability attributable to each piece of equipment does not exceed 2% of the effective usage time, counted from 8 a.m. to 6 p.m. Monday to Friday, excluding public holidays. Since this threshold was written for hardware, it should be clarified in the special clauses for software.
What happens if the buyer does not respond after acceptance testing?
For the regular service check, the buyer has a maximum of seven days to notify its decision in writing. Failing that, the result is considered positive and the services are deemed accepted. Tacit acceptance then takes effect at the end of this seven-day period. In the event of postponement, the buyer's silence for more than fifteen days after the contractor's response counts as rejection.
Which acceptance criteria should be quantified before acceptance testing?
Four categories. Functional coverage, for example one hundred percent of blocking cases and at least ninety-five percent overall. Residual defects, with zero blocking and a maximum number of major defects backed by a dated commitment to fix. Performance expressed on a quantile rather than an average, at target volume. And cross-cutting criteria, accessibility and the absence of known critical vulnerabilities. The classification of defects as blocking, major, and minor is defined before acceptance testing begins.
Read next
Guides on the same topic
Explore the topic further with a selection of complementary resources.
Jan 21, 2026
MCP n8n: create and update workflows with Claude, 2026 guide
A guide to n8n MCP: connect Claude, distinguish the instance server from MCP Server Trigger, control access, and test workflows.
Aug 26, 2026
Electronic invoicing: turning compliance into accounting automation
Electronic invoicing is reshaping workflows, tools, and data, paving the way for SME accounting automation.
Jan 07, 2026
n8n Webflow: automate your workflows no-code
Discover n8n Webflow to automate Webflow via API, CMS, and forms, connect Google, manage images, tokens, and credentials, and ensure your data reliability.